SELINA.
Renovating operating hotels, from construction through everyday use.
Renovating hotels that never closed.
Between 2016 and 2020, seven Selina properties across Costa Rica and Mexico underwent renovations and transformations involving more than 300 rooms.
Although each property differed in size, location, and target market, the underlying challenge was much the same: adapting existing buildings to a new hospitality concept while continuing to welcome guests.
Most of the work involved renovating existing spaces or converting them to different uses. Construction schedules were compressed, budgets were limited, and hotels typically remained operational at approximately 50% occupancy throughout the process.
This meant that construction could not be planned in isolation. Every intervention had to account for guest circulation, noise, staff routines, and the operational needs of spaces that were already in use.
Construction was only part of the process.
Keeping the properties operational required close coordination between construction teams, architects, engineers, suppliers, hotel management, and Selina’s various departments.
With project management based on site, decisions could be made in response to actual conditions rather than relying exclusively on plans and remote coordination. Work was organized around ongoing operations, with regular inspections to review progress, address discrepancies, and coordinate solutions as conditions changed.
Opening the renovated spaces was not the end of the process.
The following months provided an opportunity to see how the properties performed under everyday use. Construction defects and warranty matters were addressed with the responsible parties, while hotel personnel received technical training on the spaces and systems they would operate.
Just as importantly, feedback from staff and department heads revealed practical needs that had not necessarily been apparent during design or construction. Some led to further adjustments, others to entirely new improvements.
Across the seven properties, this became a recurring process: renovate, operate, observe, adjust, and repeat. Rather than treating the opening as a final milestone, it became another stage in understanding what the building needed to work better.
EXPLORE THE PROJECTS.
Select any image to enlarge it. Use the arrows below to move through the gallery.
Images will populate from Dropbox as correctly named files are added.
THE TEAM.
- ClientSelina
- Professional roleOn-site project management · client-side representation · construction inspections
- LocationsCosta Rica · Mexico
- Period2016–2020
Professional experience of the principal during an independent professional engagement with Selina, before AxiZ Studio. Photography and third-party materials require appropriate publication rights.